BHP has warned of a $1.7bn cost overrun in the development of its Canadian fertiliser site, dealing a blow to the world’s ...
Successive CEOs kept the momentum. In 2010, Marius Kloppers launched a failed $38.6 billion bid for the company now known as ...
Startup of the Jansen mine is now expected in mid-2027 and company may delay the second phase to 2031 from 2029 ...
SASKATOON - BHP Group Ltd. says the cost of the first phase of its Jansen potash project in Saskatchewan is going to be more ...
Mike Henry has delivered the sort of numbers he’s become known for. But BHP’s operational excellence make the issues at its ...
As consideration, Lifezone will pay up to $83 million, comprising a fixed payment of $10 million upon completion of funding ...
Explore more
After mining giant BHP mothballed its Nickel West business, the population of Leinster fell from 600 to 220, but long-term ...
From aggressive streetnakeds and adventure tourers to fully-faired sportbikes, this guide brings five of the most capable ...
BHP has suffered a cost blow out of $2.5bn and a delay in its Jansen potash project that injects fresh uncertainty into the ...
The size of blow out is enough to make an investor’s blood run cold just like a winter at Jansen, about 130 kilometres east ...
BHP Group, a global mining giant, announced a significant setback at its Jansen potash project in Canada, revealing a delay ...
MINING giant BHP Group on Friday announced significant delays and cost increases at its Canadian potash venture, Jansen, ...